Region | Year of Execution | Equipment | Qty | Scope of work | Supply Duration | Site work Duration | Value | Remarks |
Assam, East India | 2021 | 10KL LMO System | 5 | Supply of tank, vap & Skid & complate piping | 4 weeks | NA | 130 Lakhs | No site work |
2021 | 13KL LMO System | 4 | Supply of tank, vap & Skid & complate piping | 4 weeks | NA | 120 Lakhs | No site work |
2022 | 10KL LMO System | 10 | Supply of tank, vap & Skid & complate piping | 6 weeks | NA | 250 Lakhs | No site work |
2022 | 10KL LMO System | 1 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid, Civil work, fencing, PESO license | 4 weeks | 5 weeks | 65 Lakhs | |
2022 | 10KL LMO System | 1 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid, Civil work, fencing, PESO license | 4 weeks | 5 weeks | 55 Lakhs | |
2022 | 10KL LMO System | 1 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid, Civil work, fencing, PESO license | 4 weeks | 5 weeks | 55 Lakhs | |
Banguluru, South India | 2020 | 6KL Oxygen System | 3 | Supply of tank, vap & Skid | 6 weeks | NA | 75 Lakhs | No site work |
2021 | 13KL LMO System | 1 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid & 300 Mtr Site piping, Civil work, fencing, PESO license | 2 weeks | 2 weeks | 68 Lakhs | |
2022 | 13KL LMO System | 4 | Supply of tank, vap & Skid & complate site piping & E &C | 5 weeks | NA | 140 Lakhs | No site work |
Dubhari, East India | 2022 | 10KL LMO System | 1 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid, Civil work, fencing, PESO license | 8 weeks | 4 weeks | 55 Lakhs | |
Madhypradesh, West India | 2022 | 21KL CFS System | 1 | Supply, E & C of tank, vaporizer, pump, manifold & complete site piping & Civil work | 5 weeks | 2 weeks | 70 Lakhs | |
Maharashtra, West India | 2019 | 21KL LMO System | 1 Nos | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid, Civil work, fencing, PESO license | 4 weeks | 2 weeks | 145 Lakhs | |
2020 | 13KL LMO System | 13 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid | 3 weeks | 2 weeks | 390 Lakhs | |
2020 | 21KL LMO System | 9 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid | 5 weeks | 2 weeks | 350 Lakhs | |
2020 | 21KL LMO System | 7 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid | 3 weeks | 2 weeks | 250 Lakhs | |
2020 | 10KL LMO System | 10 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid | 3 weeks | 2 weeks | 250 Lakhs | |
2020 | 10KL CFS System | 1 | Supply, E & C of tank, vaporizer, pump, manifold & complete site piping | 2 weeks | 1 weeks | 55 Lakhs | |
2022 | 10KL CFS System | 2 | Supply, E & C of tank, vaporizer, pump, manifold & complete site piping | 4 weeks | 2 weeks | 80 Lakhs | |
2022 | 10KL LMO System | 10 | Supply of tank, vap & Skid & complate piping | 5 weeks | NA | 235 Lakhs | No site work |
2022 | 21KL CFS System | 1 | Supply, E & C of tank, vaporizer, pump, manifold & complete site piping | 8 Weeks | 1 weeks | 65 Lakhs | |
2023 | 13KL High Pressure Gas Distribution system | 1 | Supply, Installation, Errection, Testing, Commissioning of High Pressure tank, 2500 Nm3 Vaporizer, Pressure Reducing Skid-2500Nm3/Hr Flow & Site piping | 14 Weeks | 4 weeks | 40 Lakh | |
2023 | 6KL High Pressure Gas Distribution system | 1 | Supply, Installation, Errection, Testing, Commissioning of High Pressure tank, 2500 Nm3 Vaporizer, Pressure Reducing Skid-2500Nm3/Hr Flow & Site piping | 14 Weeks | 4 weeks | 37 Lakh | |
2023 | 4KL High Pressure Gas Distribution system | 1 | Supply, Installation, Errection, Testing, Commissioning of High Pressure tank, 2500 Nm3 Vaporizer, Pressure Reducing Skid-2500Nm3/Hr Flow & Site piping | 14 Weeks | 4 weeks | 32 Lakhs | |
Uttar Pradesh, North India | 2021 | 10KL LMO System | 1 | Supply, Inst, E & C of Tank, Vaporizer, PRS Skid & Entire piping at site | 5 weeks | 2 weeks | 65 Lakhs | |